PURPOSE

To test the entire One Touch Switch process from end-to-end with other CPs using test data.

ENTRY CRITERIA

  • Completed essential tests as specified in the TOTSCo Hub Test Case Doc

PREPARE FOR TESTING

  • Send in your technical pre-requisites 3 working days before your test slot.
  • Read the Integration Testing documents, available on request via the Service Desk only.
  • Complete the development of your IT stack for OTS switching.
  • Contact the service desk when you are ready to start integration testing.
  • We will pair you up with another CP (buddy) to complete testing.
  • We will set up an introductory call with you and your buddy.
  • We will share with you the test scenario document.


Following the call, you will then decide with your buddy your specific tests (in addition to the generic tests in the test scenario document), test data, test schedule.

BOOKING A TEST SLOT

  • Request a three-way testing slot via email to TOTSCo.
  • TOTSCo will confirm or propose an alternative slot.
  • Accept the Microsoft Teams meeting invite for the testing
    window.


PREPARE WITH YOUR BUDDY

  • Select and coordinate with a buddy CP to choose test scenarios.
  • Agree on a test plan.
  • Decide on the test data to use during the end-to-end tests.

STEPS TO COMPLETE INTEGRATION TESTING

Once you have successfully connected with your threeway connection you can now access the integration testing environment independently with your buddy and run your
planned tests.

ACCESS THE TESTING ENVIRONMENT

Once the three-way connection is successful, you can access the testing environment. It's important to note that while the integration testing environment is available 24/7, technical  support is only available during UK business hours (8am-5pm, Mon-Fri).

SUCCESS CRITERIA

  • End-to-end connectivity between the buddy CPs via the OTS hub
  • Completion of agreed test cases between the buddy CPs