Industry Trials build on Integration Testing by using real customer data and real switches, to enable users to gain further assurance that the OTS process will work (minimising potential consumer dissatisfaction) at OTS go-live.
Industry Trials build on Integration Testing by using real customer data and real switches, to enable users to gain further assurance that the OTS process will work (minimising potential consumer dissatisfaction) at OTS go-live.
Industry Trials build on Integration Testing by using real customer data and real switches, to enable users to gain further assurance that the OTS process will work (minimising potential consumer dissatisfaction) at OTS go-live.
Trials are conducted on behalf of the entire industry. If you are unable to participate, rest assured that you won't be disadvantaged. We will share trial results and lessons learned on a weekly basis. For non-participants, a streamlined path to go-live will be provided to ensure readiness for OTS.
Industry Trials have three phases. The initial phases, with a low degree of customer sensitivity, aim to identify any significant issues with the process and technology. The later stage involves a ramp-up in volume of switches in preparation for OTS go-live.
The industry trials approach was formulated through discussions with industry over the past year, incorporating insights from various industry test groups. It takes into account feedback received see Bulletin 42, a proposal for industry trials, and the feedback requested in December.
If you are a trial participant, you have a choice of the stage you decide to enter trials.
The entry criteria to take part in trials is as follows:
Purpose: Validating the live production environment and the end-to-end OTS process.
Type of switch: non-primary lines only. No residential customer will be impacted by the technical trial.
Entry criteria:
Trial stage duration: March and April.
Volume of switches: up to 30 per Communication Provider (CP).
Purpose: Trial a limited number of primary lines to prove the end-to-end OTS process utilising varied scenarios in a controlled manner to minimise potential consumer harm. This stage will commence following successful completion of technical trials. Staff trials will be pre-planned with TOTSCo with agreed test scenarios.
Type of switch: primary lines on pre-selected volunteer employees or friends and family.
Entry criteria:
Trial stage duration: May and June.
Volume of switches: between 30-50 gaining provider switches per CP and 30-50 losing provider switches per CP.
Purpose: Gradually increased volume of switches and scenarios to continue to validate the process and technology.
Type of switch: primary lines with no pre-selection.
Entry criteria:
Trial stage duration: July and August.
Volume of switches: a significant number of trials messages.
Trial participants play a crucial role in validating the OTS process on behalf of the entire industry and are required to:
For those of you who will not be participating in industry trials here are your steps to achieve OTS go-live:
Our hub user guide is a valuable resource, offering detailed information that complements and adds more detail to the content available on our website.
Contact us, if you would like help getting started on your OTS journey or you have any questions as you progress please do not hesitate to contact our service desk.
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.